Tirebolu-Doğankent-Kürtün Public Road Superstructure Rehabilitation is located on the axis of state highways between Giresun and Gümüşhane. The project is 2x1 single lane and 51 km long. The project consists of 40.629.32 tones of concrete foundation, 77.209.26 tones of binder, 58.953.04 tones of wearing, 52.545.52 tones of plant mix foundation, 11.519 cubic meters drainage, 22.520.64 cubic meters concrete gutter, 14.400 meters drainage manufactures.
The works carried out on 51 km highway in total were started on July 13, 2010 and completed by the end of 2010.